On September 24, 2010 Old Dominion Electric Cooperative (ODEC) withdrew its PSD air quality permit application.
This page provides information about the timeline for the previously active applications for air quality pre-construction permitting for the proposed Old Dominion Electric Cooperative (ODEC) Cypress Creek Power Station in Surry County, Virginia. No air quality permits have been issued for this source and DEQ currently has no active air quality permit applications for the project.
|
December 17, 2008
DEQ received the PSD application from ODEC
|
|
January 15, 2009
DEQ sent ODEC an Initial Letter Of Determination (ILOD) regarding the PSD application, in which additional information was requested
|
|
February 10, 2009
DEQ received the MACT application and the PSD application updates from ODEC
|
|
March 18, 2009
ODEC conducted the required public briefing for the PSD application at Gardens on the Rolfe in Dendron, Virginia
|
|
May 18, 2009
DEQ requested additional information from ODEC
|
|
October 2009
DEQ received a revision to the June 2009 Ambient Air Monitoring Quality Assurance Project Plan (QAPP)
|
|
February 26, 2010
DEQ received updated MACT and PSD information from ODEC, in response to DEQ’s letter of May 18, 2009
|
|
March 24, 2010
DEQ requested additional information from ODEC
|
|
May 14, 2010
DEQ received the Class I modeling emissions inventory protocol and modeling protocol
|
|
May 21, 2010
DEQ requested additional information from ODEC
|
|
June 30, 2010
DEQ received ODEC’s request for withdrawal of the MACT application and DEQ received information in response to the March 24, 2010 information request
|
|
July 2, 2010
DEQ sent ODEC a MACT application withdrawal acknowledgment letter
|
|
September 8, 2010
ODEC issued a press release announcing an extension of the air permit timeline
|
|
September 24, 2010
DEQ received ODEC’s request for withdrawal of the PSD application and DEQ sent ODEC a withdrawal acknowledgment letter
|