Solid waste landfill
- Part A
- Completeness review: 30 days
- Processing of complete application: 90 days (estimated)
- Public comment: N/A
- Part B
- Completeness review: 30 days
- Processing of complete application: 180 days (estimated)
- Public comment: 90 days (estimated)
Solid waste treatment and storage
- Permits-by-Rule
- Completeness review: 30 days
- Part A
- Completeness review: 30 days
- Processing of complete application: 60 days (estimated)
- Public comment: N/A
- Part B
- Completeness review: 30 days
- Processing of complete application: 120 days (estimated)
- Public comment: 90 days (estimated)
Yard waste composting
Regulated Medical Waste Full (Off-Site) Permit-by-Rule
- Permits-by-Rule
- Completeness review: 30 days (estimated)
Regulated Medical Waste On-Site Permit-by-Rule and Yard Waste Composting Permits-by-Rule
Effective upon filing complete application and required information.
Hazardous waste
- Treatment and storage
- Completeness review: 60 days
- Processing of complete application: 120 days
- Public comment: 135 days *
- Remarks: * Includes 60 days for EPA review and 45 days for public comment.
- Land disposal
- Completeness review: 60 days
- Processing of complete application: 250 days
- Public comment: 135 days*
- Remarks: * Includes 60 days for EPA review and 45 days for public comment.
- Incineration: Trial burn
- Completeness review: 60 days
- Processing of complete application: 250 days
- Public comment: 135 days *
- Remarks: * Includes 60 days for EPA review and 45 days for public comment.
- Incineration: Final
- Completeness review: 60 days
- Processing of complete application: 120 days
- Public comment: 135 days *
- Remarks: * Includes 60 days for EPA review and 45 days for public comment.
- Transportation
- Completeness review: 3 days
- Processing of complete application: 7 days
- Public comment: N/A
- Emergency permit
- Completeness review: 5 days
- Processing of complete application: 10 days
- Public comment: 30 days *
- Remarks: * Public notice occurs after permit issuance.